CDM test pile works for method of basement excavation
Piling works for crane foundation
Construction site overview
CDM piling works for method of basement excavation
Project construction site
CDM work for basement excavation
Overall construction site
CDM work for basement excavation of Tower 1 is in progress
Excavation work for crane's foundation of Tower 2 is in progress
Steel sheet pile driving for excavation of Tower 3 is in progress
Tower crane erection of Tower 4 is in progress
Piling works of Tower 5 is in progress
CDM work for basement excavation of the Podium is in progress
Overall construction site
Construction site from Dong Tay street
Preparation for basement and buildings’ foundation excavation has completed
Excavation at Tower 1 & 2 is in progress
Excavation at Tower 3 is in progress
Piling works of the Podium and all the Towers have completed
Overall construction site
Excavation works at tower 5 are in progress
Excavation works at towers 3, 5 and the podium are in progress
Excavation works at the podium between towers 3 and 5 are in progress
Excavation works at tower 3 are in progress
Excavation works at the podium between towers 1 and 3 are in progress
Excavation works at tower 5 are in progress
Overall construction site from Dong Tay street
Excavation works at tower 1 from above
Close-up excavation works at tower 1
Overall construction site
Overall construction site
Overview of the swimming pool, tower 1 & 2 construction
Overview of the swimming pool, tower 4 & 5 construction
Overview of the swimming pool, tower 4 & 5 construction
Formwork and rebar installation for ground floor slab (Tower 1) are in progress
Formwork and rebar installation for ground floor slab (Tower 2) are in progress
Formwork and rebar installation for ground floor slab (Tower 3) are in progress
Formwork and rebar installation for ground floor wall and column (Tower 4) are in progress
Formwork and rebar installation for ground floor slab (Tower 5) are in progress
Overview of the public park and lake construction
Overall construction site
Overall construction site
Formwork and rebar installtion for 1st floor (Tower 1) are in progress
Formwork and rebar installtion for 2nd floor (Tower 2) are in progress
Formwork and rebar installtion for 2nd floor (Tower 3) are in progress
Formwork and rebar installtion for 2nd floor (Tower 4) are in progress
Formwork and rebar installtion for 3rd floor (Tower 5) are in progress
T1 - Casting was completed on Floor 4.
T2 - Slab was casted on Floor 5. Formwork & rebar installation is in progress for Floor 6.
T3 - Slab was casted on Floor 5. Wall’s rebar & formwork are installing from Floor 5 to Floor 6.
T4 - Complete casting on slab of Floor 5. Formwork & rebar installation is in progress for Floor 6.
T5 - Casting was completed on Floor 6.
Overall view of towers 1-2-3-4
Overall view of towers 2-3-4-5
Tower 1: Casting works for floor L4 is completed
Tower 2: Casting works for floor L5 is completed. Formwork and rebar installation for floor L6 are in progress.
Tower 3: Casting works for floor L5 is completed. Formwork and wall's rebar installation from floor L5 to L6 are in progress.
Tower 4: Casting works for floor L5 is completed. Formwork and rebar installation for floor L6 are in progress.
Tower 5: Casting works for floor L6 is completed